I once worked at the Whyalla Steelworks at management level*. And after leaving BHP I worked for the British Iron and Steel Research Association (BISRA) in England. As a result, I know a lot about steelmaking. So, I feel competent to comment, again, on the latest crisis.
The latest crisis: From ABC News 14 September 2026
|
In short: Administrators met with workers this morning. What's next? |
Last year's crisis: From ABC News 20 Feb 2025
|
In short Prime Minister Anthony Albanese has announced a $2.4 billion joint state-federal support package for Whyalla and its steelworks. The troubled site was forced into administration by the state government on Wednesday. What's next? |
Background
AI tells us:
“The Whyalla Steelworks is a fully integrated steelworks and the only manufacturer of rail in Australia. Iron ore is mined in the Middleback Range to feed the steelworks, resulting in the distribution of finished steel products of over 90 different grades. It occupies a 1,000 ha site on the shore of False Bay, Spencer Gulf and is the largest employer in Whyalla, South Australia.
Approximately 1.2 million tonnes of raw steel is [was] produced in the steelworks each year…"
The Whyalla works was fully integrated (raw materials all the way to finished products). It was conceived by BHP to exploit rich iron ore deposits at the head of the Spencer Gulf shipped to the East coast plants, consuming backloaded coal from NSW.
This coal is converted to coke (pure-ish carbon) in the Whyalla coke ovens. Together with iron ore and limestone flux, this is used to feed the blast furnace. The product is molten iron (an alloy of iron metal [Fe] and carbon). Pig Iron.
To make steel, which has a higher melting point than Pig Iron, and many superior properties, the carbon content must be lowered and perhaps other metallic elements added.
Since 1965 this has been accomplished at Whyalla using Basic Oxygen Steelmaking (BOS) furnaces that have the additional advantage that the BOS process also consumes recycled scrap – for example: rolling-mill off-cuts; crushed cars; old rails and joists; and reinforcing bar.
While blast furnace technology has been perfected over hundreds of years, BOS technology was ‘state of the art’ in 1965 as it requires a ‘tonnage oxygen plant’, that only became widely available in the late 1950’s. The Whyalla Universal Mill, that converts the steel, produced in the BOS, into useful rails and structural steel, was also ‘state of the art’ when installed, in 1968.
At that time the molten steel was cast into ‘ingots’ then shaped into ‘blooms’ and ’billets’. In a major advance, in April 1992, a $150 million Continuous Slab and Bloom (Combination or ‘Combi’) Caster was commissioned. This was very successful and kept the plant competitive with imports but it turned out to be the last major addition to Whyalla Steelworks’ facilities by BHP, that would quit steelmaking just six years later.
In 1997 the venerable, little-old, Blast Furnace No.1 was demolished. So that now the plant relied on just one. This meant that each time this furnace had to be relined, standard periodic maintenance, no steel could be made. Relines typically take months. No iron, no steel, no income.
An integrated steelworks can be likened to a person, in which the failure of any major organ may result in the failure of the whole. And Whyalla, with aging plant and outdated technology, has seen its share of failures since the departure of BHP.
A complete upgrade was now needed if it is to compete with imported steel. The previous owner GFC's oft-promoted ‘grand plan’ for Whyalla involved something completely new and not yet commercially proven - anywhere: Green Steelmaking.
This would be totally novel to Whyalla. None of the existing steelmaking plant, nor 87 years of accumulated expertise and experience, would be required. Of the existing processes, only the continuous caster and rolling mill would have a future.
In the green steelmaking process, iron ore (oxides of iron) would be pelletised and fed to a direct reduced iron (DRI) plant from which it would pass to an electric-arc furnace to make steel.
DRI is already commercial technology, typically employing ‘syngas’ derived from coal or natural gas as the reduction agent. This strips the oxygen from iron ore at very high temperature (but below melting temperature) leaving just the iron metal and any ungasified impurities present in the ore.
Syngas is comprised of carbon monoxide and hydrogen. It is very like what we used to call ‘coal-gas’ and to burn in our homes for lighting and heating, before ‘natural gas’.
Except in some remote locations, DRI is only marginally competitive with modern blast-furnaces. DRI requires very pure iron ore and/or a secondary refinement step, making it more expensive and problematic than a traditional blast furnace.
The world’s largest steelmaker, China, and their high-tech competitors, like Korea, are continuing to build new blast furnaces, in preference to direct reduction.
To avoid carbon and or hydrocarbons, and thus large tonnages of carbon dioxide, hydrogen alone can also be employed as the reducing gas.
Back in the day, this was proposed in a British Steel paper, produced by my colleagues, entitled: ‘Nuclear Steelmaking’, in which an integrated nuclear reactor would both disassociate water, into hydrogen and oxygen, and provide the copious amounts of electricity required for the next step: melting the resulting hot-briquetted iron (HBI) in an electric-arc furnace.
But without high-temperature carbon monoxide to do the ‘heavy lifting’, well over double the amount of hydrogen is required, compared to Syngas. As some needs to be burnt for heat. This is a lot of hydrogen. And at present prices hydrogen is at least ten times more expensive than syngas.
Yet, Green Steelmaking has been attractive to South Australia, as that state often has a surplus of unused electricity, due to its over-dependence on wind power and the need to keep the lights on when the wind is uncooperative – why not make hydrogen with it, using the electrolysis of water? The hydrogen would be free – right?
All very attractive to a politician. But due to the cost of capital the hydrogen would be anything but free and there is not a hope in hell of ‘Green Steel’ being a commercial proposition at present prices, given a proper feasibility study.
So, let us hope that the billions now promised are to upgrade the existing technology, starting with an additional, more modern, blast-furnace and associated infrastructure (sinter plant and so on).
You never know, an upgraded plant might be able to compete with imports again, without seemingly bottomless Australian taxpayer support.
Whyalla Steelworks time line (from Wikipedia):
Blast Furnace No.1 was built between 1938 and 1941, blown in 1941, relined in 1965, closed in 1981 and demolished 1997.
Blast Furnace No.2 was built in 1965, relined 1981 and again in 2004.
The Coke Ovens were built in the 1960s with 2 batteries. Another battery was added in the 1980s.”
After reviewing BHP publications, I have added:
Two 120 tonne BOS vessels commissioned in 1965. Associated Tonnage Oxygen Plant.
The Whyalla Universal Mill (bar mill producing rail and structural joists) installed in 1968 (enabling the ancient, second-hand, rail mill at Port Kembla to be closed).
Continuous Slab and Bloom (Combination or ‘Combi’) Caster Commissioned in 1992
5 Feb 2025 Hydrogen plant in doubt as SA premier refuses to commit to $600m project linked to Whyalla steelworks (ABC News) Read More...
*In 1969 I joined BHP as a steel company cadet. A fellow cadet was Ron McNeilly who would later head up the Steel Division and would oversee BHP’s exit from steelmaking 28 years later.
Back in 1970 Ron and I, together with one other cadet, would go on a six-month steelworks orientation tour that would take us into all aspects of the steelmaking process, on the plant floor, often working alongside the engineers and superintendents. We spent several months at the Port Kembla and Newcastle steelworks and a shorter time in Whyalla, at that time a much smaller plant.
Ron stayed at BHP, rising through the executive ranks, while I went to the UK where I worked for British Steel, at the British Iron and Steel Research Association (BISRA) laboratories on ‘forward technologies’.